Acta Oeconomica Pragensia 2018, 26(1):25-33 | DOI: 10.18267/j.aop.593

IMPLEMENTATION OF THE REFERENCE CLASS FORECASTING METHOD FOR PROJECTS IMPLEMENTED IN A CHEMICAL INDUSTRY COMPANY

Renata Walczak1, Tomasz Majchrzak2
1 Warsaw University of Technology, College of Economics and Social Sciences
2 Basell Orlen Polyolefins Sp. z o.o.

The purpose of this article is to present an industrial application of the Reference Class Forecasting Method (RCFM) developed by Kahneman and Tversky for planning and decision-making under uncertainty. Project plans are usually prepared on the basis of detailed calculations and arrangements according to selected project management methodology. Undertakings that are planned in this manner often fail and do not achieve their goals. However, the American Planning Association recommends using the RCFM as an additional method. The article presents four groups of projects implemented by a chemical industry company over four years. A few of the projects were accomplished according to the plan in terms of triple constraint i.e. time, cost, and scope. The cost aspect was taken into account in the paper. During the study, the planned and implemented costs of 222 projects were analysed. On the basis of the distribution of cost overruns, according to RCFM, new patterns of planned costs were prepared. The Reference Class Forecasting Method, which was effective for large homogeneous projects turned out to be completely useless for various projects implemented by the chemical company.

Keywords: risk management, quantitative methods & models, technology management, Reference Class Forecasting
JEL classification: D81, G32

Published: February 1, 2018  Show citation

ACS AIP APA ASA Harvard Chicago IEEE ISO690 MLA NLM Turabian Vancouver
Walczak, R., & Majchrzak, T. (2018). IMPLEMENTATION OF THE REFERENCE CLASS FORECASTING METHOD FOR PROJECTS IMPLEMENTED IN A CHEMICAL INDUSTRY COMPANY. Acta Oeconomica Pragensia26(1), 25-33. doi: 10.18267/j.aop.593
Download citation

References

  1. Abrams, J. B. (2010). Quantitative business valuation: A mathematical approach for today's professionals. 2nd ed. Hoboken, US: Wiley.
  2. Dimov, I. T. and McKee, D. (2007). Monte Carlo methods for applied scientists. River Edge, NJ, USA: World Scientific. Go to original source...
  3. Dinsmore, P. and Cabanis-Brewin, J. (2010). AMA handbook of project management. 3rd ed. Saranac Lake, NY, USA: AMACOM Books.
  4. Flyvbjerg, B. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge: Cambridge University Press. Go to original source...
  5. Flyvbjerg, B. (2011). Over budget, over time, over and over again. In: P. W. Morris, J. K. Pinto and J. Söderlund, eds., The Oxford Handbook of Project Management, 1st ed. Oxford: Oxford University Press, pp. 321-344. Go to original source...
  6. Flyvbjerg, B., Skamris Holm, M. and Buhl, S. (2002). Underestimating Costs in Public Works Projects: Error or Lie? Journal of the American Planning Association, 68(3), pp. 279-295, https://doi.org/10.1080/01944360208976273 Go to original source...
  7. Flyvbjerg, B., Skamris Holm, M. and Buhl, S. (2004). What Causes Cost Overrun in Transport Infrastructure Projects? Transport Reviews, 24(1), pp. 3-18, https://doi.org/10.1080/0144164032000080494a Go to original source...
  8. Flyvbjerg, B., Skamris Holm, M. and Buhl, S. (2005). How (In)accurate Are Demand Forecasts in Public Works Projects? Journal of the American Planning Association, 71(2), pp. 131-146, https://doi.org/10.1080/01944360508976688 Go to original source...
  9. Fridgeirsson, T. V. (2009). The Use of Reference Classes to Forecast Risk and Uncertainty in Icelandic Projects. In: Proceedings of the 5th Nordic Conference on Construction Economics and Organisation. [online] Reykjavík: Reykjavík University, pp. 117-124. Available at: http://www.ru.is/media/publications/SoSE/5NC-2009-VOL-2.pdf#page=118 [Accessed 4 Feb. 2017].
  10. Goldratt, E. M. (1997). Critical chain. Great Barrington, MA: North River Press.
  11. Hastie, S. and Wojewoda, S. (2015). Standish Group 2015 Chaos Report, [online]. Available at: https://www.infoq.com/articles/standish-chaos-2015 [Accessed 4 Feb. 2017].
  12. Hinde, D. (2012). PRINCE2 study guide. Hoboken: Sybex.
  13. Kahneman, D. (2011). Thinking, fast and slow. Kindle edition. New York: Farrar, Straus and Giroux.
  14. Kahneman, D. and Tversky, A. (2000). Choices, values and frames. New York: Cambridge University Press. Go to original source...
  15. Leach, L. P. (2014). Critical chain project management. 3rd ed. Norwood, MA, USA: Artech House.
  16. Office of Government Commerce (OGC), (2009). Managing successful projects with PRINCE2. London: Stationery Office Books.
  17. PMBOK, (2008). A guide to project management. Body of knowledge. Upper Derby: Project Management Institute Standard Committee.
  18. Stackpole, C. S. (2013). PMP certification all-in-one for dummies. Somerset, US: Wiley.

This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International License (CC BY 4.0), which permits use, distribution, and reproduction in any medium, provided the original publication is properly cited. No use, distribution or reproduction is permitted which does not comply with these terms.