Prague Economic Papers 2019, 28(3):313-329 | DOI: 10.18267/j.pep.692

Factors Affecting the Length of Procedure in Public Procurement: The Case of the Czech Republic

Michal Plačeka, Martin Schmidta, František Ochranaa, Milan Půčekb
a Center for Social and Economics Strategies, Prague, Czech Republic
b Vysoká škola regionálního rozvoje a Bankovní institut – AMBIS, a.s., Prague, Czech Republic

The article deals with the issue of the length of procedure in public procurement. Our analysis focuses on construction contracts in 2010-2015. We apply hierarchical linear regressions to these data to identify factors that affect the length of procedure. According to our results, the duration of a public contract does not affect the standard contract price. The nature of the contracting authority, the expected value, the openness of the procurement procedure, and the method of evaluation have a statistically significant impact on the length of the contract. As for other factors regarding the length of awarding time, the use of the subcontractor, the division of a contract into parts, and a review by the Office for the Protection of Competition due extend the time required. By contrast, contracting time can be reduced by the use of outsourcing. In the end of the article, we have put forward recommendations for economic policy and further research.

Keywords: public procurement, delays, decentralization, accountability
JEL classification: H57, H72, H77

Accepted: April 23, 2018; Published: July 10, 2019  Show citation

ACS AIP APA ASA Harvard Chicago IEEE ISO690 MLA NLM Turabian Vancouver
Plaček, M., Schmidt, M., Ochrana, F., & Půček, M. (2019). Factors Affecting the Length of Procedure in Public Procurement: The Case of the Czech Republic. Prague Economic Papers28(3), 313-329. doi: 10.18267/j.pep.692
Download citation

References

  1. Ahsan, K., Rahman, S. (2017). Green Public Procurement Implementation Challenges in Australian Public Healthcare Sector. Journal of Cleaner Production, 152, 181-197, https://doi.org/10.1016/j.jclepro.2017.03.055 Go to original source...
  2. Baldi, S., Bottasso, A., Conti, M., Piccardo, Ch. (2016). To Bid or Not to Bid: That Is the Question: Public Procurement, Project Complexity and Corruption. European Journal of Political Economy, 43, 89-106, https://doi.org/10.1016/j.ejpoleco.2016.04.002 Go to original source...
  3. Borowiec, A. (2017). The Impact of Public Procurement System on the Development of Competition in the Economy in the Light of Empirical Research. Oeconomia Copernicana, 8(1), 37-50, https://doi.org/10.24136/oc.v8i1.3 Go to original source...
  4. Brezovnik, B., Oplotnik, Ž. J., Vojinovič, B. (2015). (De)centralization of Public Procurement at the Local Level in the EU. Transylvanian Review of Administrative Sciences, 2015(46E), 37-52, https://doi.org/10.1111/j.1468-0297.2006.01049.x Go to original source...
  5. Carson, S. J., Madhok, A., Wu, T. (2006). Uncertainty, Opportunism, and Governance: the Effects of Volatility and Ambiguity on Formal and Relational Contracting. The Academy Management Journal, 49(5), 1058-1077, https://doi.org/10.5465/AMJ.2006.22798187 Go to original source...
  6. Coviello, D., Mariniello, M. (2014). Publicity Requirements in Public Procurement: Evidence from a Regression Discontinuity Design. Journal of Public Economics, 109, 76-100, https://doi.org/10.1016/j.jpubeco.2013.10.008 Go to original source...
  7. Dametri, R. P. (2012). Centralization vs Decentralization of Purchasing in the Public Sector: The Role of e- Procurement in the Italian Case. In Khachidze, V. (ed.) iCETS 2012: 457-470 Go to original source...
  8. De Schepper, S., Haezendonck, E., Dooms, M. (2015). Understanding Pre-Contractual Transaction Costs for Public-Private Partnership Infrastructure Projects. International Journal of Project Management, 33(4), 932-946, http://doi.org/10.1016/j.ijproman.2014.10.015 Go to original source...
  9. Decarolis, F., Palumbo, G. (2015). Renegotiation of Public Contracts: An Empirical Analysis. Economics Letters, 132, 77-81, https://doi.org/10.1016/j.econlet.2015.04.025 Go to original source...
  10. Dosi, C., Moretto, M. (2015). Procurement with Unenforceable Contract Time and the Law of Liquidated Damages. Journal of Law Economics & Organization, 31(1), 160-186, https://doi.org/10.1093/jleo/ewt020 Go to original source...
  11. Erdis, E. (2013). The Effect of Current Public Procurement Law on Duration and Cost of Construction Projects in Turkey. Journal of Civil Engineering and Management, 19(1), 121-135, https://doi.org/10.3846/13923730.2012.746238 Go to original source...
  12. Fazekas, M., Toth, I. J., King, P. L. (2016). An Objective Corruption Risk Index Using Public Procurement Data. European Journal on Criminal Policy and Research, 22(3), 369-397, http://doi.org/10.1007/s10610-016-9308-z Go to original source...
  13. Guccio, C., Pignataro, G., Rizzo, I., (2014). Do Local Governments Do It Better? Analysis of Time Performance in the Execution of Public Works. European Journal of Political Economy, 34, 237-252, https://doi.org/10.1016/j.ejpoleco.2014.01.010 Go to original source...
  14. Lennerfors, T. T. (2007). The Transformation of Transparency - on the Act on Public Procurement and the Right to Appeal in the Context of the War on Corruption. Journal of Business Ethics, 73(4), 381-390, https://doi.org/10.1007/s10551-006-9213-3 Go to original source...
  15. Loader, K. (2010). Is Local Authority Procurement 'Lean'? An Exploration to Determine if 'Lean' Can Provide a Useful Explanation of Practice. Journal of Purchasing and Supply Management, 16(1), 41-50, https://doi.org/10.1016/j.pursup.2009.10.001 Go to original source...
  16. Loader, K. (2016). Is Local Authority Procurement Supporting SMEs? An Analysis of Practice in English Local Authorities. Local Government Studies, 42(3), 464-484, http://doi.org/10.1080/03003930.2016.1157068 Go to original source...
  17. Lundberg, S., Bergman, M. (2017). Tendering Design when Price and Quality Is Uncertain. International Journal of Public Sector Management, 30(4), 310-327, http://doi.org/10.1108/IJPSM-04-2016-0063 Go to original source...
  18. Moe, C. R., Newman, M., Sein, K. M. (2017). The Public Procurement of Information Systems: Dialectics in Requirements Specification. European Journal of Information Systems, 26(2), 143-163, http://doi.org/10.1057/s41303-017-0035-4 Go to original source...
  19. Murray, G. (2007). Strategic Procurement in UK Local Government: The Role of Elected Members. Journal of Public Procurement, 7(2), 194-212. Go to original source...
  20. Nikou, Ch., Moschuris, S., Filiopoulos, I. (2017). An Integrated Model for Supplier Selection in the Public Procurement Sector of Defence. International Review of Administrative Sciences, 83(1), 78-98, http://doi.org/10.1177/0020852316634446 Go to original source...
  21. Ochrana, F., Pavel, J. (2013). Analysis of the Impact of Transparency, Corruption, Openness in Competition and Tender Procedures on Public Procurement in the Czech Republic. Central European Journal of Public Policy, 7(2), 114-135.
  22. OECD (2000). Centralised and Decentralised Public Procurement. Sigma Papers, 2000, No. 29, Paris: OECD Publishing, https://doi.org/10.1787/5kml60w5dxr1-en Go to original source...
  23. OECD (2007). Central Public Procurement Structures and Capacity in Member States of the European Union. Sigma Paper, No. 40, Paris: OECD Publishing, https://doi.org/10.1787/5kml60qdqq0n-en Go to original source...
  24. OECD (2011). Centralized Purchasing Systems in the European Union. Sigma Papers, 2011, no. 47, Paris, OECD Publishing, https://doi.org/10.1787/5kgkgqv703xw-en Go to original source...
  25. OTIDEA (2016). Public Procurement 2010-2015: Expert Report Mapping the Area of Public Procurement in the Czech Republic. Prague. Czech Republic.
  26. Plaček, M., Schmidt, M., Ochrana, F., Půček, M. (2017). Do the Selected Characteristics of Public Tenders Affect the Likehood of Filling Petition with Regulators of Public Tenders? Prague Economics Papers, 26(3), 317-329, https://doi.org/10.18267/j.pep.616 Go to original source...
  27. Plaček, M., Ochrana, F., Schmidt, M., Půček, M. (2016). The Evaluation of Role of the Office for Protection and Competition of the Czech Republic in Regulating Public Procurement. NISPAcee Journal of Public Administration and Policy, 9(1), 97-117, http://doi.org/10.1515/nispa-2016-0005 Go to original source...
  28. Rose-Ackerman, S. (1999). Corruption and Government: Causes, Consequences, and Reform. New York, NY: Cambridge University Press. ISBN 9781107441095. Go to original source...
  29. Sanchez Solino, A., Gago de Santos, P. (2016). Influence of the Tendering Mechanism in the Performance of Public-Private Partnerships: A Transaction Cost Approach. Public Performance & Management Review, 40(1), 97-118, http://doi.org/10.1080/15309576.2016.1177558 Go to original source...
  30. Schmidt, M., Plaček, M., Ochrana, M., Půček, M. (2016). An Empirical Analysis of Post-Contractual Behavior in Public Works Contracts: The Czech Case as a Secondary Comparison with the Slovak Republic. Ekonomický časopis, 64(6), 501-518, http://doi.org/10.15240/tul/001/2016-4-007 Go to original source...
  31. Soliño, A. S., Gago de Santos, P. (2010). Transaction Costs in Transport Public-Private Partnerships: Comparing Procurement Procedures. Transport Reviews, 30(2010), 389-406, http://doi.org/10.1080/01441640903037941 Go to original source...
  32. Stloukalová, T., Jurčík, R. (2015). Relationship between Estimated Value of Public Contract and its Price. Proceedings of the 12th International Scientific Conference European Financial Systems, Brno, Czech Republic: 544-551.
  33. Tkachenko, A., Yakovlev, A., Kuznetsova, A. (2017). Sweet Deal´s: State-Owned Enterprises, Corruption and Repeated Contracts in Public Procurement. Economic Systems, 41(1), 52-67, http://doi.org/10.1016/j.ecosys.2016.12.002 Go to original source...
  34. Williamson, O. E. (1985). The Economic Institutions of Capitalism: Firms, Markets, Relational Contracting. New York, NY: Free Press.
  35. Wooldridge, J. (1999). Econometric Analysis of Cross Section and Panel Data. MIT Press.

This is an open access article distributed under the terms of the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License (CC BY NC ND 4.0), which permits non-comercial use, distribution, and reproduction in any medium, provided the original publication is properly cited. No use, distribution or reproduction is permitted which does not comply with these terms.